Victim of its success, the number of climate aid applications currently being processed has reached 14,321, and processing times are getting longer, particularly for photovoltaic installations. Faced with this situation, the government is exploring several avenues, including pre-financing.

In an answer to a parliamentary question tabled by Jeff EngelenJeff Engelen (ADR), the Ministries of the Environment, Climate and Biodiversity and the Economy have taken stock of the management and payment of Klimabonus premiums.

The response shows that 14,231 applications for aid are currently being processed, 13,212 of which relate to technical installations - mainly photovoltaic installations, often submitted in paper format. "Due to the great success of Klimabonus grants, the number of applications has risen sharply in recent years, and more recently especially for photovoltaic installations", the administration details.

Applications are often incomplete

The average processing time for the 521 Mobilitéit Klimabonus applications remains very short - less than a month, whether for cycles and pedal-assist bicycles, cars or motorbikes, car tax refunds or private charging points. On the other hand, it takes much longer to process the 13,710 Klimabonus Housing applications: it can take up to 13 months for the 11,370 technical installations applications submitted on paper. Those submitted electronically - 1,842 dossiers - benefit from slightly shorter timescales, of around 10 months.

According to the administration, these delays can be explained in particular by the fact that many dossiers are incomplete, particularly those relating to photovoltaic installations. Applications for energy upgrades and new builds are processed more quickly, with respective timescales of less than two months and up to five months.

Pre-financing of solar panels under study

To reduce these delays, the administration is suggesting several avenues: firstly, increasing staff numbers, using a subcontractor whose services will begin in November 2025, and developing a pre-financing mechanism for photovoltaic installations. This measure is intended to be extended to other aid schemes, such as the Klimabonus Mobilitéit. Installers of solar panels have also been contacted and are receiving specific assistance via the Helpdesk of the Environment Administration's Financial Aid Department, so that they can be made aware of the possibilities for improvement in compiling their applications.

In addition, the two ministries involved have announced that future aid schemes will be simplified to make the process easier: fewer supporting documents will be required, reducing the risk of incomplete applications.