Nine years elapsed between the opening of the first platform and the completion of the works. However, the opening of Howald still came a year before the most eagerly awaited rail development south of the capital.
On Wednesday 7 October, CFL officially opened the refurbished railway facilities at the Howald Mobility Hub. The modernisation of the station, which began with the opening of the first platform in 2017, was completed in late summer 2026. The final phase of the works included the installation of eight escalator units, each weighing seven tonnes, and the completion of the canopies covering the platforms and technical installations. The CFL’s press release does not specify either the amount invested in the hub or its final cost.
More than 3,000 passenger journeys are recorded every day at Howald. The station is served by an average of four trains per hour in both directions on the Luxembourg–Esch-sur-Alzette–Rodange line, in addition to two trains per hour on the Sillon Lorrain line. The two platforms, each at least 250 metres long, can accommodate trains with up to nine carriages. They are covered and feature climate-controlled shelters. Stairs, lifts and escalators, as well as a footbridge spanning the tracks, provide a link to the coach station and the tram stop.
The site also features a Park & Ride car park with 1,451 spaces, a cycle and pedestrian path, and a secure bicycle park. It is intended to support the development of Howald, Ban de Gasperich and La Cloche d’Or, three areas where housing, offices and shops are concentrated.

“Howald is now a cornerstone of national and cross-border transport,” said Yuriko Backes, Minister for Transport and Public Works. (Photo: CFL)
“Howald is now a cornerstone of national and cross-border mobility,” said Yuriko Backes, Minister for Mobility and Public Works. She believes that combining different modes of transport should make everyday travel easier and boost the country’s economic appeal.
The main focus is now on the tracks. Howald plays a central role in the preparations for the opening, in September 2027, of the new seven-kilometre double-track railway line between Luxembourg and Bettembourg.
Once it is operational, each platform will have a distinct function. The platform due to open in March 2025 will serve trains on the Luxembourg–Esch-sur-Alzette–Rodange line, as well as services connecting the north and south of the country via Luxembourg station. The platform, which has been in operation since 2017, will serve trains on the Sillon Lorrain running on the new Luxembourg–Bettembourg line.
This separation is intended to prevent a delay on one line from spreading to the other via a domino effect. The new capacity should also enable the freight service to be expanded, with the renewal of the tracks reserved for this activity.
Work on the new line is also entering its technical phase. The CFL still expects that, in 2026, track welding and further levelling will take place, along with the laying of signalling, telecommunications and fibre-optic cables, and the installation of catenary systems and electrical substations.
The year 2027 will be devoted to finishing work, inspections, rolling stock trials and connecting the line to Bettembourg station and the control centre in Luxembourg. Drivers and traffic control staff will also need to be trained before the opening, which is scheduled for September.
The Howald project forms part of the wider redevelopment of the Luxembourg South railway complex, which stretches from the Hesperange woods to Bonnevoie. This area serves the Stabling and Maintenance Centre, the Luxembourg station marshalling yard and two freight routes, including the North Sea–Mediterranean European corridor. The opening of the hub therefore marks the completion of a project that began in 2017, but its full potential will depend on the completion of the line intended to relieve pressure on the most congested rail route to the south of the capital.