Train users will have to be patient during the All Saints' Day holidays. CFL is bringing rail traffic to a complete halt on several strategic sections of the country in order to continue major infrastructure work.
No trains will be running between Luxembourg and Bettembourg or to Ettelbruck and Diekirch, from 1er to 9 November inclusive. Replacement buses will run every 5 to 30 minutes, depending on the line and the time of day, with departures from the bus station or Kirchberg.
This work includes the removal of two level crossings at Dommeldange and Colmar-Usines, replaced by safer subways for pedestrians and cyclists. A lengthy project that will have taken almost ten years from design to delivery, but essential for safety, the rail operator points out.
CFL is also continuing the metamorphosis of the Howald interchange. Following the commissioning of a new platform in September, the site will be connected to the future Luxembourg-Bettembourg line (NBS), with the installation of four points and 900 metres of track. This new infrastructure should ultimately improve traffic flow on one of the country's busiest routes.
On the Northern line, maintenance work is also scheduled between Mersch and Ettelbruck, in particular to repair damage caused by recent heavy rainfall.
CFL invites passengers to consult the timetables and substitution plans on www.cfl.lu or the portal mobiliteit.lu, and to give preference to existing bus routes for their daily journeys.