Between the planning permission being granted and the ground-breaking ceremony, a crucial part of the work often goes unseen. Behind the scenes, the architect coordinates the necessary procedures, studies and stakeholders to transform an “approved” project into one that is “ready for construction”.

After months of deliberation, sketches, revisions and discussions, planning permission has finally been granted. For the client, this often represents the long-awaited green light. For the architect, it marks, above all, the transition to a new phase.

Long before the plans are submitted to the local council, a large part of our work involves identifying and coordinating the constraints that will shape the project. The General Urban Development Plan (PAG), the Local Urban Development Plan (PAP), building regulations, site layout, building dimensions, accessibility or specific site conditions: behind every plan lies a process of analysis and decision-making. Depending on the project, various approvals, such as that from the CGDIS, may also be required.

Once these details have been finalised, the application for planning permission can be submitted. Provided the project complies with the regulations and the application is complete, planning permission from the local authority can sometimes be granted relatively quickly. However, “approved” does not yet mean “ready to build”.

Other permits may fall under the remit of different authorities or government departments. A road permit from the Department of Public Works may be required in the vicinity of a state road. Nature conservation, water management, cultural heritage or “commodo/incommodo” procedures may also require specific steps to be taken. For the architect, the challenge lies in anticipating these procedures and incorporating them into the project schedule.

At the same time, a crucial – though often less visible – phase begins: transforming the “approved” project into a “buildable” one. The planning permission drawings set out what can be built; the construction drawings specify how it is to be built.

It is often at this stage that our work becomes least visible, even as coordination intensifies. The building’s structure, construction details, waterproofing, façade, HVAC, plumbing and electrical systems must all form a coherent whole. A decision in one discipline can quickly have consequences for several others.

Next come the tender documents, the calls for tenders and the analysis of the contractors’ bids. The technical decisions take shape and the initial cost estimates are finally compared with actual market prices. Between obtaining planning permission and the ground-breaking ceremony, the architect’s role is therefore also to act as a link: between the authorities and the client, between design and technical aspects, and between plans and contractors.

Planning permission answers the first question: “Do we have the right to build?” The planning process that follows must resolve another: “How are we going to build it?” Then inevitably comes the next question: “How much will it actually cost?”