The ‘Wandpark Eschduerf’ project involves the installation of a 6MW wind turbine connected directly to the Haute-Sûre Lake water treatment plant. Developed by Soler and Sebes, the project combines renewable energy generation with drinking water supply. Photo: Sebes

The ‘Wandpark Eschduerf’ project involves the installation of a 6MW wind turbine connected directly to the Haute-Sûre Lake water treatment plant. Developed by Soler and Sebes, the project combines renewable energy generation with drinking water supply. Photo: Sebes

In Eschdorf, wind power is set to support the drinking water supply. Soler and Sebes launched the ‘Wandpark Eschduerf’ on Thursday 11 June, a project that combines a new-generation wind turbine with the Haute-Sûre Lake treatment plant to secure its power supply.

A 6MW wind turbine linked to a drinking water treatment plant. This is the project that Soler and the Esch-sur-Sûre dam water authority (Sebes) officially launched on Thursday in Eschdorf. Named ‘Wandpark Eschduerf’, it aims to supply part of the electricity needed to treat water from Lake Haute-Sûre. For Sebes, which supplies nearly 50% of Luxembourg’s drinking water and up to 70% during dry summer periods, the challenge also lies in securing its energy supply.

Pumping water from the lake and treating it requires a significant amount of electricity. Sebes has already fitted its new production site in Eschdorf with solar panels that cover around 10% of its energy needs. To supplement this generation, the syndicate has chosen to partner with Soler on a new-generation wind turbine.

The project provides for a direct power supply to the treatment plant, as well as several other sources of electricity. The site has a connection to the Creos high-voltage grid as well as a link to the Esch-sur-Sûre hydroelectric power station. This configuration should enable the facilities to continue operating even in the event of a widespread failure of the national grid.

“It is an honour for Sebes to launch a first in Luxembourg: a drinking water infrastructure powered by wind energy,” says André Weidenhaupt, president of Sebes. “The future of water supply in Luxembourg requires a break from fossil fuels.”

A first in the Benelux

The wind turbine selected is an Enercon E-175, a model that Soler describes as a first for the Benelux region. With an installed capacity of 6MW, it is expected to generate around 21.5GWh of electricity per year. According to the project developers, this output corresponds to the annual consumption of around 4,800 households, or nearly 19,100 people.

The facility will be located 1,200 metres from the nearest homes. Soler also estimates that it will prevent around 4,021 tonnes of CO2 emissions per year.

“This is the first E-175 wind turbine to be installed in Luxembourg, with a capacity 40 times greater than that of the first wind turbines built in the country,” explains Soler’s managing director, Paul Zeimet. “It is also the first time that Soler has partnered with a critical infrastructure operator such as Sebes.”

Plans for public participation

The initial discussions regarding the project date back to 2021. A public information meeting held in 2024 provided an opportunity to present the technical specifications of the facility, its environmental assessment, and its development model.

Soler now plans to open up the share capital of the companies within the wind farm to the public one year after the wind turbine comes into operation, subject to confirmation of its productivity and profitability. This scheme forms part of the approach the company has developed for several of its energy projects.

“We are delighted to see our joint project with Sebes taking shape,” says Paul Zeimet. “This partnership is only just beginning.”