Ultimately, the competition was won by Metaform architects. However, four other projects were submitted on this occasion. This is the project designed by Christian Bauer & Associés Architectes (CBA) in collaboration with Baumschlager Eberle Architekten.
The group has designed a project based on the conservation of the existing structure and considers that the building as a whole deserves to be protected as such. CBA considered a plan without any structural intervention, particularly in the load-bearing ceilings. This was a major gamble, as it went against what had been proposed by the CFL. Only the removal of partitions and the addition of lifts and staircases were envisaged, as well as the renovation of the entire building, with the aim of making it more energy efficient.

The project by CBA and Baumschlager Eberle Architekten is a complete redesign of the historic building on the Place de la Gare. (Illustration: CBA/Baumschlager Eberle Architekten)
In order to meet CFL's wish to accommodate 1,200 people in the new building, an extension was designed to be built onto the existing building and to extend towards the tracks. Another part of the building, which could function independently, is built on top of the adjacent building.
A larger extension is also made possible and is envisaged as an elevation on the building along the quays. This addition would constitute a visible signal in the neighbourhood, becoming a high-rise building.
In the plans offered by CBA, the inner courtyard has been covered and can be used in a semi-public way. It’s served by the Rue du Chemin de Fer and the station platform.
On the ground floor, the entrance hall and the connection to the back area can be found. This is the meeting and communication area, a representative space of the CFL. It is characterised by light boxes that serve as conference and work rooms and that naturally illuminate these spaces.
The workspaces are developed on platforms and are flexible and adaptable to all office configurations.
Several roofs, which are greened, are accessible as terraces and provide outdoor working and relaxation spaces for employees.
The facades are glazed and solar protection is provided by glass printed with photovoltaic elements that also produce part of the electricity needed to operate the building.
Technical data
Architects: Christian Bauer & Associates Architects, Baumschlager Eberle Architeckten
Civil engineer: Ney & Partners
Technical engineer: Amstein + Walthert
Landscape architect: HDK Dutt and Kist
Project manager and coordinator: IC Lux Ingénieurs-Conseils
This story was first published in French on Paperjam. It has been translated and edited for Delano.