"It will be a construction site, and not an easy one—not just to build, but above all because of the consequences for the surrounding area," Mayor Lydie Polfer told councillors during a Monday afternoon city council meeting. Photo: Paperjam archives

"It will be a construction site, and not an easy one—not just to build, but above all because of the consequences for the surrounding area," Mayor Lydie Polfer told councillors during a Monday afternoon city council meeting. Photo: Paperjam archives

From 2033, the planned Route d’Arlon branch would offer CHL patients, staff and visitors a tram every six to eight minutes, with connections to buses from the west. The 2.1km scheme includes a 600-metre covered trench, but its eastern development site, the hospital approach and access during building works all raised questions at Monday’s council meeting.

Luxembourg City councillors unanimously approved the municipality's €57m contribution to the tram extension towards the Centre Hospitalier de Luxembourg (CHL) on Monday 16 November, despite warnings about the future hospital interchange and disruption along Route d'Arlon.

Mayor Lydie Polfer (DP) also revealed that court pleadings in a challenge to the Place de l'Étoile development plan are scheduled for 26 September 2028. She maintained that the proceedings should not obstruct the tram project, while acknowledging that important questions remain about its implementation.

"It's good that it is moving forward, but there is still a lot of work to do," said Claude Radoux (DP), who supported the financing decision but questioned the final interchange arrangements. The city's contribution represents one-third of the €171m investment, excluding VAT at April 2025 prices, with the remaining €114m authorised nationally under legislation enacted in September.

The new branch will connect with Luxembourg's existing tram network rather than operate as a separate shuttle. The government estimates a journey of approximately five minutes between the new Étoile station and the CHL interchange, with passenger services planned for the first quarter of 2033.

How the tram will reach CHL

Gabriel Boisante (LSAP) welcomed the extension but warned of a potential bottleneck around the future hospital's parking facilities and the proposed tram stop. Referring to concerns raised by the hospital's project steering committee, he questioned how vehicles would enter and leave the site alongside tram operations.

Although several meetings had already taken place, he was not aware of a satisfactory solution having emerged. He argued that the city, as a contributor to the project, should ensure the tram was properly integrated with the hospital's future operations.

Radoux identified a choice between an approach stopping near CHL's new building and one continuing to the planned transport interchange on the Strassen side. He also claimed that CHL had not been informed about a particular design option affecting a pavement near its maternity facilities.

Polfer replied that the hospital-access difficulties had been raised with CHL and expressed confidence that a solution would be found. In a separate written response to Paperjam, CHL had reported providing Luxtram with parking statistics and building plans and holding meetings covering car parks, ambulance routes and pedestrian access. It described these as preparatory work to identify the necessary adaptations.

The wider western connection was another concern for Radoux. "It cannot be the aim simply to stop at CHL," he argued, calling for faster progress on the proposed Boulevard de Merl and continuation of the tram towards the future P+R Ouest.

The €171m scheme finances the extension as far as the CHL interchange. The further western connection remains a separate project, for which the mobility ministry told Paperjam in October that no timetable could yet be announced.

A dispute at Place de l'Étoile

At the other end of the line, François Benoy (déi Gréng) warned that the tram's progress was closely connected to the longstanding redevelopment of Place de l'Étoile. He called on the city to use its available powers to prevent delays to the development project from holding up the tram.

Polfer explained that neighbouring residents had challenged the local development plan in court. She insisted the legal dispute should not jeopardise the tram's timetable, despite the September 2028 date she gave councillors for the pleadings.

Benoy also challenged the financial implications of the approximately 600-metre covered trench along Route d'Arlon. He argued that difficulties obtaining the land needed for surface tracks had contributed to the decision to adopt a more expensive underground solution.

"We are finding a rather Luxembourgish solution, which means building a tunnel because we lack the means to argue too much with property owners," he told the council.

Polfer rejected the suggestion that land acquisition difficulties were the principal reason for the underground alignment. She explained that a surface route would have prevented residents of certain buildings from reaching their underground car parks, creating problems beyond the question of property ownership.

Difficult works ahead

The published construction programme envisages work beginning in spring 2029, testing in late 2032 and commercial operations early the following year. During Monday's discussion, Polfer referred tentatively to the end of 2029 as the starting point for construction, without formally announcing a revision to the published timetable.

The mayor acknowledged that rebuilding Route d'Arlon would be difficult for people who live, work and travel along it.

"It will be a construction site, and not an easy one—not just to build, but above all because of the consequences for the surrounding area," she told councillors.

Polfer explained that the city, the state and Luxtram would need to coordinate the successive stages and find alternative routes while maintaining access for residents and other road users. She acknowledged that passing through sections under construction would be difficult.

Radoux proposed reconvening the tram project steering committee used during earlier construction phases, involving representatives of businesses, residents and other affected groups. He argued that the Route d'Arlon extension would have more direct consequences for established neighbourhoods than some previous sections.

No detailed timetable for traffic diversions at individual premises emerged from Monday's debate. For people living or doing business along Route d'Arlon, the practical question after the financing vote is when their section of the road will be affected and how access will be maintained.