Whether you take the train or the car to go to work, the summer is going to be complicated for some daily trips because of numerous works.
Starting with the CFL, border commuters will have to combine train and bus to reach Luxembourg station from Thionville or Metz(L90) between Saturday 16 July and Sunday 7 August. During the same period and until Sunday 28 August, no TGV will be running between the Luxembourg capital and France.
CFL promises a "replacement bus service". They are not yet able to specify how many buses there will be per day. "The details of the buses will be available at the latest two weeks before the start of the blockades in question.” However, the TER Grand Est network has already published a timetable of the replacement buses. Many peak hour journeys involve a change at Bettembourg. For example, the train that leaves Metz at 7.43am and Thionville at 8.18am will arrive in Bettembourg at 8.34am, where another bus will leave at 8.40am for Luxembourg.
No Luxembourg-Bettembourg train for three weeks
This is due to the closure of the Luxembourg-Bettembourg section for the redesign of the southern part of Luxembourg station. "At the end of the works, each train line will have its own dedicated track in Luxembourg station. This will make it possible to reduce the crossing of trains from different lines in the station and thus reduce the transfer of delays from the trains of one line to the trains of another line,” the CFL indicates
This work will therefore also affect passengers coming from Rodange and Esch-sur-Alzette(L60). As no trains will be running between Luxembourg and Bettembourg between 16 July and 7 August, there will be no stops at Howald during these three weeks either. The Pétange-Rodange section will also be blocked between 20 August and 4 September, and again on the weekend of 17 and 18 September.
Although trains will be able to run between Luxembourg and Bettembourg again from 8 August, this will be done gradually and traffic will remain reduced throughout the rest of August and until 11 September on both lines L60 and L90. Detailed timetables are not yet available, but the TER Grand Est network has already indicated that, for the L90 line (the one between Metz and Thionville), "the journey between Luxembourg and Bettembourg will be made using the national CFL trains of line 60".
Longwy-Pétange, Trier and Arlon also affected
Border workers from Longwy will be able to reach the capital easily this summer, except on the weekend of 2 and 3 July, when no trains will run. On the other hand, those who go as far as Pétange will not have any trains between Saturday 20 August and Sunday 4 September.
Other disruptions are to be expected in the north. On the L10 line, no trains will run between Luxembourg and Gouvy, Ettelbruck, Diekirch, Kautenbach and Wiltz between 20 and 28 August. The blockage will continue between Ettelbruck and Wiltz until 11 September, although trains will be able to run on the weekend of 3 to 4 September.
Between Oetrange and Trier, line L30, there are no trains between 9 and 31 July.
And finally, no trains between Kleinbettingen and Arlon, on line L50, between 12 and 19 August.
Still 70 on the A3 under construction
Taking the car to escape the disruptions will not always be the best idea for border workers, who will also no longer be entitled to unlimited teleworking. Because on the road too, work is continuing.
The A3 especially will be affected by this. "Work on lot 1 (Croix de Gasperich - Livange interchange) will continue until September 2024," explains the roads and bridges administration. "The traffic will operate, except for occasional blockages of one lane for exceptional works at night or during weekends, always on two lanes in both directions, at 70km/h at the places affected by the works. However, the work will be stopped during the collective holidays in August, like many in the country. Some exceptions will be "the redevelopment of the Gasperich bank, the PC8 cycle path in Belval and the N40 (new N3)".
The disruptions caused by the works on the Gasperich bank are, however, concentrated "at the weekend", the administration assures. For example, the motorway has been closed between the Gluck roundabout and the Hesperange interchange since 9pm on Friday 17 June and until 5am on Monday 20 June. Diversions are in place, via the boulevard de Kockelscheuer, the CR231 (boulevard F. W. Raiffeisen) and the Hesperange interchange.
No impact on the N40
The portals of Cita (Control and information of the traffic on the motorways) and of the public works report a hundred works in progress or to come in all, some of them lasting only one day. Among the roads closed are the N27 between Bourscheid-Moulin and Lipperscheid from1 June to 30 November, and the N17 between Bettel and Bivels from 16 to 31 July. Closer to the capital, the CR230 between Luxembourg and Strassen remains closed from 2021 until 29 July 2022. The N13 will also be closed between Frisange and Aspelt between 27 June and1 July.
On the A13 between S7-E (Kayl: entrance towards Esch) and B-S6 (Schifflange: exit from Bettembourg), two lanes will be closed towards Pétange between 21 June and 10 July.

Here are all the works in progress or to come announced by Cita. (Photo: Screenshot Cita.lu)
Another major project, but one that will not impact traffic, is the construction of a new road: the N40 at Bonnevoie, scheduled for 11 September, with the arrival of the tram.
Elsewhere in the capital, "we often receive information a week in advance" about the works, explains the City of Luxembourg. According to its latest press releases, between 13 June and 28 July, rue Wurth-Paquet and rue Astrid between Place de France and 1 rue Wurth-Paquet will remain blocked.
On both road and rail, other projects can of course always be added.
This story was first published in French on Paperjam. It has been translated and edited for Delano.