Preparatory work on the Belval Park Sports Centre (estimated cost: €123.9m) was also discussed. A fitness trail is planned on the green roof. Photo: Fonds Belval

Preparatory work on the Belval Park Sports Centre (estimated cost: €123.9m) was also discussed. A fitness trail is planned on the green roof. Photo: Fonds Belval

Luxembourg MPs followed up the financial aspects of the Belval Fund and CFL infrastructure projects. No budget overruns were noted for Fonds Belval projects, while two CFL projects could potentially exceed the budget.

As part of a twice-yearly parliamentary committee exercise, MPs carried out a financial review of the major infrastructure projects of the Fonds Belval and the CFL in the presence of the minister for mobility and public works, Yuriko BackesYuriko Backes (DP). For the Fonds Belval’s major infrastructure projects: everything is in order, according to the minister.

In more detail, Backes said that for the projects currently being implemented--for which MPs have passed a financing law--the budget is being respected and no budget overruns have been noted or are expected. As far as the Human Sciences Centre is concerned, work should be completed this year. The estimated budget is €69.2m. The Finance Act was adjusted from €67.4m to €77.2m.

The estimated cost of urban development and the extension of the Maison du Savoir car park is €63.7m. The funding bill had already been adjusted from €58m to €64.2m. The north and south wing laboratories and the engineering test hall (estimated cost: €157.7m), the equipment for the buildings in the first phase of construction of the Cité des Sciences (estimated cost: €140m), and the preparatory work for the Sports Centre (estimated cost: €123.9m) were also mentioned.

Ettelbruck multimodal hub concerned

As far as the CFL projects are concerned, two are likely to exceed the budget initially allocated. “CFL representatives presented an outline of the infrastructure projects currently underway. They pointed out that two projects are potentially at risk of going over budget. Requests for increases will be made (and presented) when the time comes,” they stressed to MPs.

The two projects in question are the multimodal hub at Ettelbruck station, where the potential cost overrun is due to the adaptation of the initial project for the rail section, and the modernisation of switches and crossings on the line from Luxembourg to Troisvierges, where the potential cost overrun is due to a price increase. The cost of the future interchange at Ettelbruck station had already been increased to 196.6 million euros by 2021, compared with the €156.5m initially forecast. The modernisation of the Luxembourg-Troisvierges line, initially expected to cost €36.7m, had also been revised to €57.5m in 2023.